Construction downstairs
Looking down over the construction site of the eastern section of the new Prasad distribution hall...
...and one day later.
   
Preparing shuttering for the ground level beams.
Pouring the beams.
   
Starting the machine...
...to settle the concrete into the form.
   
Touching up by hand.
   
About half way through the day's work.
Downstairs in the western section of the building, the lower walls start to grow.
   
Outside view.
Inside, the ground floor.
   